Turn days into daily shares
Let A, B, C do x, y, z of the job per day. A team that needs 6 days does 1/6 of the job each day.
Finishing in n days means doing 1/n of the job per day.
8.EE.C.8Convert To AlgebraFind A's share
Take the B-and-C team away from the whole team; what is left is A.
Whole team minus a sub-team leaves the missing member.
7.NS.A.3Identify SubproblemsA's daily share is the whole team's daily share minus the B-and-C team's daily share.
Why?
Working at a steady rate, the work done is the rate times the days, so a team that finishes the whole job in days does of it each day.
Why?
When people work side by side, the team's daily work is just each person's share added together, so and .
Why?
Taking away from undoes adding it and leaves , so .
Find B's share
Take the A-and-C team away from the whole team; what is left is B.
Same subtraction, different sub-team.
7.NS.A.3Identify SubproblemsAdd A and B
Together A and B do the sum of their daily shares.
Rates of people working side by side add.
7.NS.A.3Convert To AlgebraCall the whole job 1; then every team is just a sum of daily shares, and subtracting teams picks out individuals.
- Turn days into daily shares
- Find A's share
- Find B's share
- Add A and B